Prioritise beneficiation of iron ore and the production of steel as a solid foundation for industrialisation.

Kept

Tsingshan Iron Ore and Chrome/Coke Value Addition Project

Veritas

    

July 19, 2022

The Tsingshan Iron Ore and Chrome/Coke Value Addition Project straddling the Chivhu and Mvuma districts of Mashonaland East and Midlands provinces, respectively, has recorded the following progress: construction of the Carbon Steel Plant is progressing well; the foundation of the steel plant structure and supporting infrastructure are 70% complete; most of the blast furnace components are at the steel plant site and ready for installation; and the construction of the power line from Sherwood to Manhize is on course.

 